Bank works more than 50 metres and all other bank works not otherwise described
This activity applies to carrying out all other bank works (including any alteration to the bank height).
This includes:
- Installation of new bank works greater than 50 metres
- Alteration of the bank height (e.g. floodwalls and embankments)
- Alteration of existing bank works greater than 50 metres which does not meet the maintenance criteria
- Removal of bank works more than 50 metres
- Installation or removal of bank works which cannot comply with GBR or registration standard conditions.
Authorisation level
Permit
Public consultation
We may publicly consult on applications that, due to their nature or location, have higher likelihood of environmental impact and community impact.
Read more about public participation and engagement
Fit and Proper Person tests
Fit and Proper Person tests apply to this activity. You will be asked in your application if you have any relevant convictions held by you or any additional persons.
Read more about Fit and Proper Person tests
Fees and charges
An application fee applies to the application of a new authorisation for this activity.
An annual activity fee does not normally apply to this activity.
Read our charging information for further information on application and annual activity fees.
Information on the application fees to transfer, vary or surrender a permit that authorises this activity, is in our charging information.
Permit conditions
Permits may contain both standard conditions and conditions specific to the activity and location. The conditions of your permit will be decided when we assess your application. This is to ensure that the appropriate limits and controls are in place to minimise pollution and protect the environment.
If you carry out an activity under a Permit authorisation you must comply with the conditions set out in your authorisation. It is an offence if you do not comply with the conditions.
SEPA will not authorise this activity if it poses an unacceptable risk to the environment.
How to apply
In this section you can find out how to apply for a new authorisation and how to apply for a variation, transfer and surrender of an existing authorisation.
New applications
You can apply for a new permit for this activity using our digital application service.
If you are applying for new permit, we would encourage you to contact us with any pre-application enquiries before submitting your application.
Step 1: Download your activity form
You will need to download and complete the following activity form. The completed form will be submitted as part of your application:
Step 2: Provide supporting information
For a new permit, you will also need to provide the following supporting information:
- Non-technical summary of your application
- Details on materials and techniques to be used
- Drawings of the structure
- Report assessing risk to fish (if required)
- Details of whether the activity may impact on SSSIs, SACs and SPAs
- Reasons for carrying out the activity
- Photographs of the area where the activity is to be carried out
- Options appraisal
- Details on why selected option is the best practical environmental option
- Proposed mitigation of environmental impacts
Step 3: Submit using our digital application service
You can submit your completed application using our digital application service.
Make an application for a new authorisation
Help and guidance
- Glossary of terms
- WAT-G-022 EASR Guidance: Engineering: Activity Guide: Bank works
- WAT-G-029 EASR Guidance: Engineering Sustainable Bank Protection
- WAT-G-027 EASR Guidance: Engineering: Maintenance, replacement and removal of existing engineered structures
- WAT-G-030 EASR Guidance: Engineering: Meeting Good Practice
- WAT-G-031 EASR Guidance: Engineering: Permit Application Guide
- WAT-G-035 EASR Guidance: Drawings for Permit level water activities
- WAT-G-008 EASR Guidance: Assessment of impact on Protected areas from inland water activities
- WAT-G-032 EASR Guidance: Fish Protection
- WAT-G-033 EASR Guidance: Inland surface waters and river subtype
- WAT-G-034 EASR Guidance: Construction works and silt/pollution mitigation
- EASR-G-001 EASR Guidance: Invasive Non-Native Species (INNS)